Analisis Kinerja Waktu dan Penerapan Building Information Modeling pada Proyek Pembangunan Jasmine Park Apartment Bogor

Time Schedule Analysis and Building Information Modeling Application on Jasmine Park Apartment Bogor

  • Ahmad Ulil Albab IPB University
  • Erizal IPB University
Keywords: BIM, S Curve, Tekla Structure, Time Schedule

Abstract

Increasing of certainly development requires jobs with high productivity, effectiveness and efficiency. The application of BIM up to four-dimensional modeling (4D) using Tekla Structure software is a solution because it can analyze time performance, determine the causative factors in the event of delays and actions to overcome them. 3D modeling included modeling of foundations, columns, beams, slabs, stairs, and roofs. 4D modeling is conducted by adding work schedule to the 3D modeling that had been made. Time performance analysis was performed using the S-curve method for all buildings in Tower Green Jasmine Park Apartment Bogor construction project. Time performance analysis using the S curve found that this project experienced delays with the highest negative deviation value happened in June 2020 by -13.67%. The main delays in the project occured in procurement of MEP logistics and weather conditions. Work acceleration is carried out by increasing working hours and increasing the number of workers.

 

Downloads

Download data is not yet available.

References

Ardani. 2009. Analisa Penerapan Manajemen Waktu pada Proyek Konstruksi Jalan [skripsi]. Sumatera Utara (ID): Universitas Sumatera Utara.

Berlian PCA, Adhi RP, Hidayat A, Nugroho H. 2016. Perbandingan efisiensi waktu, biaya, dan sumber daya manusia antara metode Building Information Modelling (BIM) dan konvensional (studi kasus: perencanaan gedung 20 lantai). Jurnal Karya Teknik Sipil. 5(2): 220-229.

[DepPU] Departemen Pekerjaan Umum. 2006. Pedoman Teknis Fasilitas dan Aksesibilitas pada Bangunan Gedung dan Lingkungan. Peraturan Menteri Pekerjaan Umum Nomor 36/PRT/M/2006. Jakarta (ID): Departemen Pekerjaan Umum.

Eastman C, Teicholz P, Sacks R, Liston K. 2011. BIM Handbook: AGuide to Building Information Modelling for Owners, Managers, Designers, Engineers and Contractors. New Jersey(US): Wiley.

Firoz S, Rao SK. 2012. Modelling concept of sustainable steel building by Tekla Software. International Journal of Engineering Research and Development. 1(5): 18-24.

[KemenPUPR] Kementerian Pekerjaan Umum dan Perumahan Rakyat. 2018. Pembangunan Bangunan Gedung Negara. Peraturan Menteri Pekerjaan Umum dan Perumahan Rakyat Nomor 22PRT/M/2018. Jakarta (ID): Kementerian Pekerjaan Umum dan Perumahan Rakyat.

Sulistio W, Andi. 2016. Perbandingan penjadwalan proyek menggunakan kurva “s” dan cpm network pada proyek “x” di Surabaya. Jurnal Dimensi Utama Teknik Sipil. 3(2): 1-8.

Sutomo Y, Anhar S, Firmanto A. 2016. Analisis manajemen proyek pembangunan kantor pt. prima multi usaha Indonesia. Jurnal Konstruksi. 5(4): 435-444.

Published
2021-04-28
How to Cite
1.
Ulil AlbabA, Erizal. Analisis Kinerja Waktu dan Penerapan Building Information Modeling pada Proyek Pembangunan Jasmine Park Apartment Bogor: Time Schedule Analysis and Building Information Modeling Application on Jasmine Park Apartment Bogor. J-Sil [Internet]. 2021Apr.28 [cited 2024Apr.20];6(1):11-2. Available from: https://jai.ipb.ac.id/index.php/jsil/article/view/35039
Section
Research Articles